#12. You have produced a detailed plan of deliverables and the associated activities needed to complete your project. You want to establish a tracking mechanism to report project programs in terms of time, scale, cost and functionality. Which three actions should you take? (Choose three)
#15. After completing the second phase of a three-phase project you determine that the resources available for this last phase are inadequate. Because of concerns that were raised in the initial two phases, you feel that the customer will not want to add additional resources for this last phase. Which two actions help ensure a more successful completion of the final phase? (Choose two)
#19. You received an invoice from your contractor in a fixed-price contract with a payment schedule tied to the completion of milestones. What is the MOST important thing to review?
#20. You are developing a scope of work for a project that will utilize limited technical resources.A change has been requested by one of the technical resources to modify a user input screen. Which individual must approve this request?