#54. You are the project manager for a telecommunications project. Your team proposed a change in some equipment configurations to streamline the cutover process. The change is not excepted to delay any project milestones and the proposed cost is minimal. It most cases, this change should be _____.
#58. At the project implementation meeting, you find out the end users of the new application were not consulted during the design phase. In order to implement this new application what can you do to obtain end-user buying?